Keep the parts of the prototype that encode the research and replace the parts a pilot will break: login, data storage, logging and deployment. A 2–3 week audit decides which is which, and it protects the largest line in your budget, since engineering typically takes 25–40% of a Phase II software budget.
How do I move a Phase I prototype to a Phase II production platform without rewriting everything?
What to keep and what to replace
A Phase I prototype proves the intervention works. It was not built to hold 20 classrooms of student data for a semester, and it does not need to be thrown away either. The research logic is the asset; the plumbing is the risk.
| Component | Usual decision | Why |
|---|---|---|
| Content, item banks, scoring rules | Keep | This is the intervention your proposal describes; rewriting it changes the treatment |
| Prompts and model logic | Keep, then version | The study needs to know exactly which prompt each student saw |
| User interface | Keep, then harden | Teachers already know it; fix accessibility and slow screens |
| Login and roles | Replace | District single sign-on, teacher and student roles, no shared passwords |
| Data storage | Replace | A schema built for analysis, with consent and de-identification designed in |
| Event logging | Replace or add | Prototypes log what the developer needed, not what the efficacy study needs |
| Deployment | Replace | One pipeline with staging, tests and rollback instead of a laptop |
On most prototypes we see, the top three rows survive and the bottom four get rebuilt. That is a foundation replacement, not a rewrite.
Start with a two-to-three-week audit
Before any Phase II code is written, someone who has shipped production software reads the prototype end to end. The audit should produce four documents you can hand to a program officer or a new hire:
- A component map marking each part keep, harden or replace, with the reason.
- A target architecture: hosting, database, authentication, logging and how the kept code plugs in.
- A data plan: what is collected, where it lives, how it is de-identified, and what the data use agreement will need to say.
- A milestone plan tied to the proposal’s aims, with hours per milestone.
Skipping the audit is how teams end up rewriting twice: once in a hurry before the pilot, and again when the first build cannot produce the dataset the analysis plan requires.
The path from prototype to pilot, with durations
The approach that avoids a rewrite is to build the new foundation underneath the working prototype, moving one piece at a time, so there is always a version teachers can use. Durations below are typical for a small team and vary with how many districts and data sources are involved.
| Step | Typical duration | What exists at the end |
|---|---|---|
| Audit and architecture | 2–3 weeks | Component map, data plan, milestone plan |
| Foundation | 6–10 weeks | Real login and roles, new database, deployment pipeline, tests on the kept logic |
| Logging and data export | 3–5 weeks | Event schema matched to the analysis plan, de-identified export |
| District readiness | 2–4 weeks, overlapping | Technical disclosure package, privacy documentation, load test |
| Soft launch | 2–3 weeks | Two or three teachers using it before everyone logs in |
A focused 30-day sprint can take a working prototype to a small, district-approved pilot when the scope is tight. It cannot also deliver the full multi-site platform; that is what the remaining Phase II months are for.
Budgeting the engineering across milestones
Take a hypothetical Phase II award with an $800,000 total budget. At 25–40%, engineering is $200,000–$320,000. The top of that range is for multi-site studies, AI components or integration with district systems such as a learning management system.
| Milestone | Share | At $240,000 (30%) |
|---|---|---|
| Audit and architecture | 10% | $24,000 |
| Foundation and data layer | 35% | $84,000 |
| Pilot readiness and district review | 30% | $72,000 |
| Study support, fixes, data exports | 25% | $60,000 |
At $85 an hour, $240,000 is about 2,800 engineering hours over the award. Keep the last milestone: pilots break at the worst moment, and a fix during data collection is part of the study, not an overrun.
What the funder and the district are reading for
Program officers read a Phase II plan for whether the team can deliver software that runs in real settings and becomes a product. A plan that says the graduate student will keep extending the prototype reads as a research project. A plan with an architecture, a test strategy and named milestones reads as a company.
Reliability is also research validity. If saves fail for one classroom or audio lags on school Chromebooks, that classroom’s data is noise. Clean, versioned logging is what lets the efficacy study say which students saw which version of the intervention.
Districts read for privacy and security: where data is hosted, who can see it, how FERPA obligations are handled, and how data is deleted. Your institution’s counsel or compliance office signs off on those answers; the engineering team makes sure the system actually does what the documents say.
On data rights, keep the code in repositories your organization owns, with the vendor working inside them. SBIR data rights protections apply to the small business holding the award, so a vendor should not own the platform you were funded to build.
When the graduate student should keep building
- The Phase II plan is still a lab study with one site and no school data leaving the lab.
- The student will stay for the whole award and has shipped production software before.
- The work left is mostly content and research design, not infrastructure.
Bring in a team when real student data, district review or multiple sites enter the plan. We built the prototype that helped an EdTech team win $1M in Phase II funding, then built the production platform, and the pattern held: the research team kept owning the intervention while we owned the foundation under it.
Frequently asked questions
Can we keep our Phase I code at all, or does Phase II need a rewrite?
Usually you keep the content, scoring rules, prompts and much of the interface, because those encode the intervention. Login, data storage, logging and deployment are typically replaced. A 2–3 week audit tells you which parts of your specific codebase fall where.
How much of a Phase II budget should go to software engineering?
Engineering typically takes 25–40% of a Phase II software budget. Multi-site studies, AI components and integrations with district systems push it toward the top of that range. Split it across milestones that match the aims in your proposal.
How long does it take to get from prototype to a classroom pilot?
A tightly scoped pilot can be ready in about 30 days if the prototype already works. A full multi-site platform with district review, research-grade logging and a deployment pipeline usually takes three to six months. The audit at the start sets the realistic date.
Who actually does the work, and what if the first project doesn’t work out?
Charlie scopes every project and makes the architecture calls, and Smplfy’s own engineers build it. The first project has a fixed scope, and you read a written scope before committing. A retainer starts only if you choose one.
Who owns the code if an outside team builds our Phase II platform?
Your organization should own it, in repositories and cloud accounts under your control. SBIR data rights are meant to protect the small business holding the award, so a vendor should not hold the platform. Have your counsel review the contract terms on ownership and data rights.