Break the build into four to six milestones that match your proposal’s aims, and pay for each one only when acceptance tests your team runs pass. A workable split is 15% at scope sign-off, 50% across build and pilot-ready release, 20% during the pilot and 15% held until the final dataset and code are handed over.
What should a fixed-price milestone contract for a grant-funded pilot look like, and what acceptance criteria should it include?
What the contract needs to contain
A fixed-price contract works for a pilot when the scope is written down before the price is. Your sponsored programs office will have its own template; these are the parts that template usually lacks for software.
- A written scope listing every feature the pilot needs, traced to an aim in the proposal.
- A milestone schedule with a deliverable, a date, an acceptance test and a payment for each.
- An acceptance procedure: who tests, on what devices, within how many days, and what counts as a defect.
- Change-request rules for anything not in the scope.
- Data handling terms: what student or participant data the vendor touches, where it is stored, and the data use agreement it operates under.
- Ownership and handover: who owns the code, the data and the deployment accounts at the end.
Your institution’s counsel or compliance office signs off on the FERPA, data use and data rights language. The vendor should explain its technical choices in writing so they can review them.
A sample milestone schedule
This example assumes a 12-week build before a one-semester pilot. The dollar amounts use an illustrative $100,000 contract so the percentages are easy to read; your total will differ.
| Milestone | Timing | Deliverable | Acceptance test | Payment |
|---|---|---|---|---|
| M1 Scope and architecture | Weeks 1–2 | Signed spec, data model, logging schema, draft district disclosure | PI approves spec; every feature maps to a proposal aim | 15% ($15,000) |
| M2 Core build | Weeks 3–8 | Working app on staging with teacher and student roles and event logging | Scripted walkthrough of 10 core tasks passes on the district’s devices; every action writes a log row with user ID and timestamp | 25% ($25,000) |
| M3 Pilot-ready release | Weeks 9–12 | Production deployment, roster import or SSO, data export, disclosure package | Load test at twice the pilot’s user count; export matches the analysis plan’s variables; district IT questions answered | 25% ($25,000) |
| M4 Pilot support | Pilot semester | Fixes, weekly data exports, monitoring | Severity 1 defects fixed within one business day; 99% uptime in school hours | 20%, paid monthly |
| M5 Closeout | 2 weeks after pilot | Final dataset, documentation, code and account handover | Dataset re-imports into your analysis; a second engineer can deploy from the docs | 15% ($15,000) |
M5 doubles as the holdback. A vendor that has been paid 85% still has a reason to deliver clean data and documentation, which is the part most often left unfinished.
How to write acceptance criteria you can check
An acceptance criterion is a test with a pass or fail result that someone on your team can run in a day. "The dashboard is user-friendly" is not one. "A teacher can assign a problem set to a class of 30 in under two minutes on a Chromebook" is.
- Name the environment. List the devices, browsers and network conditions, ideally the district’s own. Research code that works on a lab laptop often fails behind a school content filter.
- Test the data, not just the screens. Require that a scripted session produces exactly the expected log rows, with no missing or duplicated events. Clean logging is what makes the efficacy study possible.
- Set an acceptance window. Ten business days to test and report is common; many contracts treat silence after that as acceptance.
- Classify defects. Severity 1 blocks a pilot task and blocks payment. Severity 2 and 3 go on a written list fixed in the next milestone, so one cosmetic bug does not stall the schedule.
- Never tie payment to research outcomes. Learning gains and teacher adoption are the study’s findings, not the vendor’s deliverable. Tie payment to reliability, data completeness and handover.
Change-request rules
Scope will move once teachers see the software. The contract should make that cheap to handle and impossible to slip in silently.
- Every change is a written request; the vendor replies within three business days with the effect on cost and dates.
- A small contingency pool, often about 10% of the contract, covers minor changes without a new agreement.
- Swapping one feature for another of equal size needs only a signed note, not a change order.
- Any change that moves the pilot start date needs the PI’s written approval.
- Feature freeze during the pilot: only Severity 1 fixes ship once students log in, so every participant uses the same version.
The freeze is a research requirement as much as an engineering one. A program officer reviewing your results will ask whether the intervention changed mid-study.
What the funder and the district will look for
Milestones that mirror the proposal’s aims and budget justification make progress reports easy to write and show a program officer a research project with a managed build, not an open-ended software company. Keep the vendor’s milestone names consistent with the proposal’s language.
Under SBIR and STTR, data rights generally sit with the small business awardee. If the vendor is your subcontractor, the contract should say the code written for you is assigned to you, and list any pre-existing vendor tools licensed rather than assigned. Have counsel confirm the wording against the award terms.
The district disclosure package belongs inside a milestone, not after it. We took a research prototype to a district-approved classroom pilot in under 30 days: 20 teachers, two districts, 100+ framework-compliant problems generated, and the disclosure work ran in parallel with the build from the first week.
Frequently asked questions
How many milestones should a grant-funded pilot contract have?
Four to six is usually right for a build of two to four months plus a pilot. Fewer than four puts too much money behind each payment; more than six turns the project into paperwork. Each milestone should end in something your team can test.
Should I pay a software vendor a deposit up front?
Pay for the scope milestone rather than a bare deposit. A signed specification, data model and logging plan are worth about 15% of the contract and protect you if the engagement stops there. Avoid paying more than that before working software exists.
What if the first project with Smplfy doesn’t work out?
The first project has a fixed scope, and you read the written scope before committing to anything. A retainer starts only if you choose one. Charlie Meng scopes every project and makes the architecture calls, and Smplfy’s own engineers build it.
Who owns the code a vendor writes under an SBIR award?
Data rights under SBIR and STTR generally belong to the small business awardee, so the subcontract should assign the code written for the project to you. Vendors may license pre-existing tools instead of assigning them, which should be listed by name. Your counsel should confirm the language against your award terms.
Is fixed price or hourly better for a pilot build?
Fixed price suits a pilot with a defined scope and a funder expecting predictable spend against a budget line. Hourly suits exploratory work before the scope is clear; we bill that at $85 an hour. Many teams use hourly for discovery, then fixed-price milestones for the build.