A Phase I deliverable has three parts: a working demo of the risky claim your proposal said was feasible, evidence that it worked, and a final report tying both to your objectives. Plan a demo of about 15 minutes on a stable, deployed build, and budget 100 to 230 engineering hours beyond the prototype. It need not be production software.
What should a SBIR Phase I deliverable look like when the software has to be demoed to a program officer?
What a program officer is judging in Phase I
Phase I exists to establish technical merit and feasibility. Phase II is where the product gets built. A program officer watching your demo wants to know whether the core idea works, whether you measured it honestly, and whether your team can carry it into a larger award.
So the software has one job: show the technical objectives from your proposal working, end to end, on real or realistic inputs. Polish, scale and extra features don’t help your case. A demo that crashes, or that clearly runs on hard-coded data, does real damage, because it makes the reviewer doubt the feasibility claim itself.
Reread the objectives section of your funded proposal before you plan anything else. Every artifact below should map to one of those objectives, using the same wording.
The artifact list
These are the things a complete Phase I package contains when software is the deliverable. The hour figures are typical engineering effort on a small education or learning-science prototype. They don’t include research time.
| Artifact | What it contains | Typical engineering effort |
|---|---|---|
| Working demo | A deployed build at a stable URL or on a test device, scripted to a 10–15 minute walkthrough of each objective | 40–120 hours beyond the prototype itself |
| Feasibility evidence | The measurements behind each claim: accuracy, latency, completion rates, usability results from a small user test | 20–40 hours for logging and export |
| Demo script and backup | A written run order, seeded test accounts, a recorded video of the full demo in case the network fails | 8–16 hours |
| Technical summary | Architecture diagram, stack, where data lives, known limits, what changes in Phase II | 10–20 hours |
| Final report | Objectives, methods, results, and the Phase II plan; the software sections draw on the items above | 10–20 hours of engineering input |
| Code and data handoff | Repository in the awardee’s account, a README a new engineer can follow, a data dictionary for logged events | 8–16 hours |
Altogether that is roughly 100 to 230 engineering hours on top of building the prototype. The low end assumes the prototype already runs reliably and logs what you need. The high end is for prototypes that only run on one laptop, or that log nothing.
What is enough for Phase I, and what waits for Phase II
Most Phase I budget trouble comes from building Phase II software too early. Use this split to decide what to build now.
| Concern | Enough for Phase I | Deferred to Phase II |
|---|---|---|
| Core feature | The feature that proves the hypothesis, working end to end | Secondary features, settings, admin screens |
| Users | A handful of test accounts or one small pilot group | Rostering, SSO, district-wide onboarding |
| Data logging | Every event the feasibility analysis needs, timestamped, exportable | Dashboards, real-time analytics, researcher self-serve tools |
| Privacy | No real student PII unless an approved IRB protocol and data agreement cover it | Full FERPA-aware design and the district technical disclosure package |
| Reliability | Stable for the demo and the small test; one-command deployment | Automated tests across the codebase, monitoring, multi-site uptime |
| Interface | Clear and usable; matches the flow you describe | Accessibility review, visual design system, mobile support |
The exception is logging. If the efficacy question you’ll ask in Phase II depends on an event, start logging it in Phase I. Retrofitting an event schema later costs more and leaves your early data incomparable with what comes after.
Preparing the demo: a six-week path
- Weeks 1–2: map each proposal objective to one screen or action in the demo. Cut anything that doesn’t map to an objective.
- Weeks 2–3: move the prototype off the developer’s machine onto a hosted environment (Firebase, AWS or similar) with one deployment command, so the demo build matches what you tested.
- Weeks 3–4: make sure logging captures the feasibility measures, then run the small user test and export the results.
- Week 5: freeze features. Fix only bugs that show up during rehearsals of the demo script.
- Week 6: record a backup video, seed fresh test accounts, and write the technical summary from the frozen build.
Each week you’re late on the first three steps pushes the feature freeze back by a week. Don’t cut the freeze: a feature added three days before a demo is the most likely thing to break during it.
When to keep the graduate student building, and when to bring in a team
If the prototype already runs on a hosted build, the student who wrote it understands the research logic, and the remaining work is mostly analysis, keep them on it. Bring in engineers when the build only runs locally, when data saves unreliably, or when you are already writing the Phase II proposal and need its technical section to be credible.
We built the prototype that helped an EdTech team win $1M in Phase II funding, then built the production platform that followed. Keeping the Phase I build small paid off: the logging and data model carried forward, and the interface was rebuilt for scale.
Whoever builds it, the code should live in the awardee’s repository. SBIR data rights protect the small business’s technical data generated under the award. Your company’s counsel should check how any contractor agreement handles ownership and licensing before work starts.
Frequently asked questions
Does a SBIR Phase I demo need to be production-ready software?
No. Phase I is about feasibility, so the demo has to show the core technical objectives working reliably on realistic inputs. Scale, full privacy compliance and secondary features normally belong to Phase II.
How long should a Phase I software demo for a program officer be?
Plan 10 to 15 minutes, scripted to walk through each technical objective from the proposal in order. Keep a recorded backup video and pre-seeded test accounts in case the live build or the network fails.
Can I use real student data in a Phase I prototype?
Only if an approved IRB protocol and the relevant data agreements cover it. Many Phase I teams use synthetic or de-identified data for the demo. Your institution’s IRB, compliance office or counsel decides what is permitted.
What feasibility evidence should go in a Phase I final report?
Report the measurements behind each technical objective, such as accuracy, latency, task completion rates or small-sample usability results, and describe how each was collected. Exported logs and a data dictionary make the evidence checkable and prepare the Phase II efficacy design.
How much engineering time does a Phase I deliverable take beyond the prototype?
Typically about 100 to 230 hours for deployment, logging, the demo script, the technical summary and the code handoff. The low end assumes the prototype already runs on a hosted build and logs the needed events.